Wednesday, December 9, 2020

Chinas Railway for Laos:
Track laying has arrived at Luang Prabang at the end of 2020

Open Google Map of China-Laos Railway with pictures of construction:




Find technical informations, list of planned stations and maps here.


Update 26.12.2020

The Laos-China Railway Co. is to develop areas surrounding railway stations in Vientiane Capital, Vientiane Province, Oudomxay, and Luang Prabang. The government of Laos signed a Memorandum of Understanding with the company, reports laotiantimes.com.

Xiang Ngeun Number 3 Tunnel in Luang Prabang Province has been drilled through on 29 september. Now all of the 75 tunnels of China Laos Railway have been constructed.


Update 31.12.2020

Track laying fro China-Laos-Railway has arrived in Luang Prabang at the end of December 2020.




Update 10.12.2020

The track laying of the China-Laos-Railway project, undertaken by CREC, has exceeded 100 km and has reached Vang Vieng Station in Laos in July 2020, what means that 25 percent of the track was laid. In November 2020 the track laying reached Ban Sen No.2 Tunnel.



See the development of Luang Prabang railway station:


Read: The China-Laos railway: a way out of poverty or a white elephant in waiting?

In September 2020 the 9 km long Ban Phoukeu tunnel in Muang Nga province was drilled through by China Railway No. 8 Engineering Group.


In September 2020 the main building of Nateuy station was finished by China Railway Construction Engineering Group (CRCEG).



Update 20.5.2020

Friendship Tunnel 友谊隧道 crossing the border between Laos an China in Boten with a total length of 9,959 meters has been drilled through by China Railway No. 2 Engineering Group (CREC-2) after 37 months of work. See pictures.

Track laying has started in Vientiane. And now tracks have been laid in the first tunnel, Baan Nong Khai tunnel in Vientiane province.




Update 27.3.2020

Near Vientiane the first 500 metres of railway tracks have been laid. After reduced working during the coronavirus outbreak in China the track lying period has been compressed. The plan is to lay 1,5 kilometers of track every day. Read more.




Picture by Aero Laos on Facebook


Update 23.3.2020

Boten Special Economic Zone has fallen silent due to the coronavirus pandemic, reports rfa.org. Construction works have been stopped and stores and restaurants are closed, because few Chinese managers, technicians or tourists are showing up. Chinas Peopke Daily, a government controlled newspaper, turns it like this: "China’s investment projects in Laos gradually resume operation amid the epidemic outbreak". The work on crossborder friendship tunnel has resumed according to Crec-2. Only "some" of China’s investment projects have resumed their production and construction according to this report. One example is Vientiane Saysettha Development Zone, co-founded by China Yunnan Construction and Investment Holding Group Co., Ltd (YCIH) and the Vientiane Municipal Government. The Vientiane-Vangvieng Expressway construction has officially resumed on February 10 according to this report (also constructed by China Yunnan Construction and Investment Holding Group Co.).
on 15.3.2020 China Railway Wuhan Electrification Engineering Group Co., Ltd. (WEEG) planted the first engineering pole for overhead contact system at the construction site of the China-Laos railway project in Vientiane, Laos. Also the power supply project, running along the China-Laos railway through five provincial administrative regions in northern Laos, has started. Planned are 20 circuits of 115 kV transmission lines with the total length of 268 km and 635 power towers and extend 11 bays in 10 substations, in order to supply power from the state-run Electricite du Laos grid to 10 railway traction substations. The project is invested and built by a joint venture, namely Laos-China Power Investment Company, co-sponsored by China Southern Power Grid (CSG) and the state-run Electricite du Laos, and implemented mainly by CSG’s engineering companies.


Update 28.2.2020

Construction work on tunnels in Vientiane province is filling a creek and other local waterways with waste released by boring, polluting the water and harming the livelihoods of local residents, reports rfa.org. Water in the Houay Pamom Creek in the area of the Vang Vieng district’s Phahom village is murky and clouded. “Chemicals are flowing from Kai district, where a railway tunnel is being bored. The railway workers are spraying liquid cement onto the tunnel wall,” one village resident said. Houay Pamom Creek is a tributary of the larger Nam Song River, a popular location for swimming, tubing, and kayaking. Another Nam Song tributary — the Nam Lik River — was polluted more than a week ago by waste released from the construction of another railway tunnel, with the run-off killing nearly 50 kilograms of fish. “Chinese workers have been releasing chemicals that kill the fish, and the authorities have warned us not to use the river’s water or eat fish taken from the river,” a resident of Viengko village near the town of Vang Vieng said.

Right now, there are no informations available, how the coronavirus outbreak impacts the construction of China-Laos-Railway with a lot of Chinese workers. Xinhuanet just shows "epidemic prevention measures". But it is known that some CREC-5 engineers cannot return to their position in Laos and part of the construction materials' transportation has been halted in China as thestar.com.my reports.


Update 16.2.20

The Rebirth of Casino Town Boten, Laos: A one hour documentary by Channel News Asia:




Update 5.5.2019

See #chinalaosrailway in the bigger picture, as part of China's Belt-and-Road-Strategy on #BeltandRoad Google Map

The Kunming-Vientiane Railway in a Study by Center for Global Development (Washington): The Economic,Procurement, Labor, and Safeguards Dimensions of a Chinese Belt and Road Project.

Update 26.4.2019

Thailand, China, and Laos have signed a Memorandum of Cooperation (MoC) on the development of a rail line between Nong Khai and Vientiane in Laos. A new bridge across Mekong River will be the connection between #chinalaosrailway and Thailands highspeed railway. Read Bangkok Post. Find more informations about the development in Thailand on #BeltandRoad Google Map.


Update 26.3.2019

A video by Xinhua news agency shows the start of the beam-laying process for Nam Khone River Bridge 南柯内河特大桥 in the north of Vientiane. See the video.


Update 4.3.2019

The construction of Yuxi-Mohan railway and Boten-Vientiane railway lead to a new construction boom in the so called Beautiful Boten Specific Economic Zone. According to Laotian media Chinese investors want to pure more than $1.5 billion into the new development. China Haicheng Group 中国海诚集团积 is one company involved. They got funding from Hong Kong Fuk Hing Travel Entertainment Group Ltd according to Vientiane Times. Fuk Hing Travel Entertainment Group? Its leader Wong Man Suen was the partner of the Laos authorities for the closed Golden Boten City. "It comes as a surprise to learn the Lao officials have decided to give Wong yet another chance", writes forbes.com. Read more: After Golden Boten City fell in the Hand of Criminals: The second Chance

Update 25.2.2019

As important as the railway in Laos is the connection from the Lao border to Yuxi in Yunnan, from where an existing railway line leads to Kunming. China is building the 503.9 km long Yuxi-Mohan railway 玉磨铁路, also called Yumo Railway, with very high speed through rugged mountains. It counts 133 bridges and 91 main tunnels. Yumo railway will be electrified and have double-track from Yuxi to Jinghong and single-track from Jinghong to Mohan. Get an overview about the progress and find Yuyi-Mohan Railway 玉磨铁路 Google Map.


Update 10.1.2019

Chinese Railway Project in Laos Leaves Farmers in the Lurch: The railway has displaced more than 4,400 families from their land, many of these families have still not been compensated, reports rfa.org. Rattanamany Khounnivong, vice minister at the Lao Ministry of Public Works and Transport, told RFA late last year that those who lost houses and did not have places to live would get paid first, while those who lost farmland might get paid later. According to ABC Laos News’ Facebook page, Khounnivong said at a railway project committee meeting in November last year that of the $300 million that the government must pay out in compensation for losses related to the project, only $156 million has been paid. According to rfa.org the government must therefore borrow money from China to pay the rest this year.


Lao Villagers Reject Plans For China-Invested SEZ in Vang Vieng: The project, managed by the Chinese firm Lao-Vang Vieng New Area Development Company, will affect 22 villages lying to the west of the Xong river, reports rfa.org. Signed by the Lao-Vang Vieng Company last year in a memorandum of understanding (MOU) with Laos, the project will run in three phases over 15 years at a cost of U.S. $5.5 billion, and is expected to create 50,000 jobs, according to Lao media sources.



Update 14.12.2018

Picture of Luang Prabang Mekong Bridge 琅勃拉邦湄公河特大桥, planned 1458.9 Meters long


Picture by marhas


Picture by marhas


Picture by marhas


Picture by marhas


Picture by marhas



Update 12.12.2018



"Defaming Laos-China Railway is Ignoring Lao People’s Future": Chinese writer Zeng Ren argues on Chiang Rai Times, that the Laos-China railway "will become an important pillar of Laos’ economic growth". He gives the following data about expropriation of land: "About 3,000 hectares of land will be permanently taken over and 800 hectares of land will be temporarily used. Some 4,411 households will be affected due to the construction of the railway". He goes on: "Lao government is now seeking the opinion of relevant parties on the compensation standard. According to the requirements of railway projects, the compensation for land in different sections differs and is mainly based on whether the land is connected to national highways, provincial highways, village roads, or have no road access. Villagers affected by the railway will also be paid for their houses and apartments, as well as small buildings such as kitchens, sundries, garages, shops and animal houses. In addition, the developers of the railway will compensate people for crops and fruit trees that must be uprooted due to the railway construction. (...) The government’s compensation standard is 320,000 kip – 3.5 million kip per square metre (about US$37-US$410 per square metre). Plus other compensation for farmland, homesteads, young crops and so on, the amount of compensation will be considerable and equal to the annual income of local people."


Update 3.12.2018

How Asia Fell Out of Love With China’s Belt and Road Initiative: "Countries are discovering that the promise of Xi Jinping’s signature infrastructure program is too good to be true", writes bloomberg.com.


Update 1.11.2018

1,158-m-long Nateuy No 1 tunnel on the China-Laos Railway in Luang Namtha has been drilled through by China Railway No.5 Engineering Group (CREC 5). Huang Zongwen, a senior official with the China Railway No. 5 Engineering Group (CREC 5), told Xinhua the construction of the Nateuy No. 1 Tunnel, with 1158 meters, was started on June 3, 2017. "That the tunnel passes soft rocks all the way in the mountain, brought some difficulties in construction and especially, affected the digging pace," Huang said. See pictures.




Update 9.10.2018

Thailands Deputy Prime Minister Somkid Jatusripitak complained Monday that the development of the high-speed Thai-Chinese railway from Bangkok to Nong Khai is lagging behind schedule, as Bangkok Post reports. The route is divided into two major phases. The first is Bangkok-Nakhon Ratchasima, which is 253km in length and set to cost 179 billion baht. The second phase runs from Nakhon Ratchasima to Nong Khai province.


Update 1.10.2018

The Chinese contractor told Xinhua the concrete casting for the first block of the Luang Prabang cross-Mekong River bridge' continuous beam along the China-Laos Railway was completed on September 17. Yan Haiyong, CPC party secretary of the China Railway No 8 Engineering Group (CREC-8)'s railway project department, who is in charge of the construction of the two bridges across the Mekong along the China-Laos Railway, said that the Luang Prabang railway bridge with a total length of 1458.9 meters, is a key project of the China-Laos Railway. According to Yan, the bridge's continuous beam design has high technical standards and is difficult to construct with pier-side bracket. The first block of the continuous beam has a length of 12 meters and consumes a concrete volume of 266 cubic meters. (Reported by steelguru.com.


How is China's New Silk Road transforming Vietnam and Laos? See documentary by Channel News Asia:




Update 8.9.2018

After days of heavy Monsoon rains, that caused floods in Luang Prabang province, a bridge across Mekong river has collapsed into the river. It served to construct the new railwy bridge across the Mekong near Luang Prabang.


Picture from this video of the collapse.


Update 27.8.2018

The Chinese-built railway through Laos is worth half of that little nation’s GDP, writes washingtonpost.com. In a report by two researchers from Harvard’s Kennedy School, former Australian foreign minister Gareth Evans is quoted as saying Laos and Cambodia, each of which has borrowed more than $5 billion, are now “wholly owned subsidiaries of China.” Meanwhile Malaysias new Prime Minister Mahathir has cancelled two multi-billio dollar Chinese projetcs because Malaysia can’t repay its debts. “We do not want a situation where there is a new version of colonialism,” Malaysia’s leader told Chinese Premier Li Keqiang. One of the projects, dubbed the East Coast Rail Link, would have connected the South China Sea with strategic shipping routes in Malaysia’s west, providing an essential trade link. The other was a natural gas pipeline in Sabah, a Malaysian state on the island of Borneo.


Update 25.8.2018

In Phu Din Daeng, a village of 200 people about eight kilometers outside of Vang Vieng town, people have been told they should leave their homes to make way for the Laos-China railway. The people in Phu Din Daeng are living next to a giant construction site, near the planned Vang Vieng Railway Station.

Until now some 53 tunnels have been bored through mountains at a combined length of 37,314 meters, while 47 of the 167 bridges to be built for the line are under construction, reports chiangraitimes.com.

Laos’ cash commitment is US$720 million, of which US$250 million will come from the national budget over the next five years and the remaining US$470 million borrowed from the Export Import Bank of China at a 2.3% interest with a 35-year maturity after a five-year grace period, reports chiangraitimes.com.

With a project cost of nearly one-third of the country's copy6-billion GDP, there are concerns that the debt burden on Laos will outweigh the benefits. Public debt reached 68% of GDP in 2016 (it is less than 50% in Thailand), raising the debt distress level from "moderate" to "high" in the recent World Bank/IMF Debt Sustainability Analysis, as Bangkok Post reported.

The Ganlanba Bridge(橄榄坝特大桥) is 3.5 km long and has 108 supporting columns(桥墩). It has been constructed on the China side of the railway in Jinghong city, Yunnan province. The last(最后的) supporting column of the bridge has been installed(安装), reports chinaplus.cri.cn.

Read also: Chinese Tourist ‘Invasion’ Feared As High-Speed Laos-China Railway Will boost visitor numbers dramatically. In Luang Prabang Chinese low-cost retail chain Miniso opened a shop in June on Sisavangvong Road. In expectation of more regional visitors, many town-centre Luang Prabang residents have sold or rented out their properties to Chinese, South Korean or Vietnamese investors. The Mekong Sunset Guest House, for example, previously operated by a Lao national, is now run by a Chinese family from Guangxi province, reports South China Morning Post.


Update 18.6.2018

Recently, the pier No. 214 of Nanke River Bridge 楠科内河特大桥 in Laos was successfully poured. This is the longest bridge of the railway section built by the China Railway Second Bureau.




Update 23.11.2017

Chinas railway project in Laos is "set to be completed in 2021", reports Global Times, but the network reprots difficulties as well. Huang Hong, head of China-Laos railway commanding department under China Railway Group Ltd, says, that at mid-October "we've completed 14,925 meters in the channel excavation work", while the total length of the construction tender is 244.5 kilometers, including 45 tunnels and 99 bridges.

Xu Liping, an expert with the National Institute of International Strategy at the Chinese Academy of Social Sciences, underlines that the project is one between two nations, and so far not an intercontinental project extended to Thailand. But the project only makes full sense, if trains from China can go through to Thailand and down to Singapore.

And the China-Laos rail project faces some difficulties. For example, funds are not always allocated on time, and Laos lacks some of the needed construction materials like cement, Huang Hong said.

Zhao Xiang, director general of the Laos-China Railway Company, said according to Xinhuanet that in less than six months, site preparation has been completed for the construction of four stations; foundation construction of nine bridge piles have finished; 86 holes for construction of 46 tunnels have been prepared, of which 15 are key tunnels.

More than 4,400 Lao families are being forced to relocate to make way for the Lao-Chinese high-speed railway, reports rfa.org, by citing Rattanamany Khounnivong, deputy minister at the Lao Ministry of Public Works and Transport and one of the heads of the construction unit. The ministry is working with the provincial task force committees to finalize compensation schemes for those who are forced to relocate, Rattanamany said. Workers have been blasting tunnels in mountains, building bridges and roads, and clearing land for stations and substations along the planned rail line in the three northern provinces of Luang Namtha, Oudomxay, and Luang Prabang since construction on the railway got under way late last December.

In Thailand construction work has been delayed for the initial 3.5-kilometre stretch of the Thai-Chinese high-speed railway in Nakhon Ratchasima, Transport Minister Arkhom Termpittayapaisith said. The project's environmental impact assessment (EIA) report is still pending approval according to Bangkok Post.

Picture by Thai PBS
Planned railway from Klang Dong to Pang Asok Station


Update 23.4.2017


Boken-Vientiane rail route auf einer größeren Karte anzeigen

China's mammoth project to construct a railway from southwest China's Yunnan Province through Laos to its capital Vientiane is advancing now. Hundreds of trucks carrying machinery and equipment for construction have entered Laos, Vientiane Times reported. Preparations are now underway to start the boring of tunnels.

The 417-km railway will have 75 tunnels with a combined length of 197.83 km and work is expected to begin before the upcoming rainy season, Deputy Minister of Public Works and Transport and Chairman of the Laos-China Railway Project Management Committee, Mr Lattanamany Khounnivong, told Vientiane Times. Officials in charge have negotiated with villagers whose land is needed for the railway and have handed over their land to Chinese contractors. Six Chinese contractors will carry out construction of the USD 5.8 billion railway, with completion slated for 2021.

China Railway No 2 Group Co Ltd is responsible for the construction of Muang Phonhong section, as we learn by chinadaily. According to this source construction of the project is scheduled for five years with investment of some 40 billion Chinese yuan (USD 5.8 billion), 70 percent of which comes from Chinese investment and the rest 30 percent from Lao side.

China Railway Group (CRG) has signed a RMB 8.1 billion (US$ 1.2 billion) agreement to build the first three sections of the Boten-Vientiane Railway Project according to khl.com.

"The Nation" shows a picture of the Boten End of one tunnel, where boring has begun. Also in the province of Luang Prabang preparations are underway by China Railway No.8 Engineering Group, see pictures showing a tunnel near Luang Prabang.

Construction has begun, but questions remain. Discussions concerning loans and interest rates are ongoing between Laos and China, says Agatha Kratz, an associate policy fellow with the European Council on Foreign Relations, according to asiasentinel.com. Another skeptic is Ruth Banomyong, the director of the Center for Logistics Research at Thailand’s Thammasat University. Asiasentinal quotes her: “The challenge will come when Laos will have to repay,” she warned. “Will they have sufficient revenue generated to repay? This is doubtful as the financial feasibility study done by the Chinese does not have realistic assumptions.” According to a paper by Lao government Laos gets a Chinese loan of 480 Million US Dollars at 2.3 percebt rate per year to pay for 50 Million US Dollars, while Laos has to borrow the rest at the rate of 3 percent. See the paper in Lao: ເອກະສານໂຄສະນາເຜີຍແຜ່ນຳພາແນວຄິດກ່ຽວກັບໂຄງການກໍ່ສ້າງທາງລົດໄຟລາວ-ຈີນ.


See map of the Boten-Vientiane-Railway-Line and read more technical details.



Update 10.3.2015:

China's mammoth project to construct a high-speed railway from southwest China’s Yunnan Province through Laos to its capital Vientiane is more and more in delay: The government of Laos tries to get a better loan interest rate from China, as Bangkok Post reports. Beijing has offered a US$500-million loan with a 3% interest rate for 20 years according to Vientiane Times. The estimated costs now: US$6.8 billion. The Lao and Chinese governments should be responsible for 40 percent of the total cost, while state enterprises of the two countries should jointly be responsible for sourcing the remaining 60 percent.

Delays are not new for this project. "Beijing is believed to be waiting for the Thai parliament to approve a planned £41 billion infrastructure upgrade, which will include a high-speed rail line from the Laos border to Bangkok, before signing off on the loan", reported telegraph.co.uk in January 2014.

The railway risks to create a financial desaster for Laos: Laos plans to borrow £4.5 billion from Beijing to pay for its section of the railway. This is almost 90 per cent of Laos’s annual GDP of £5.2 billion. The loan will make Laos the world’s fourth most-indebted nation after Japan, Zimbabwe and Greece - "trouble for a poor country", wrote The Economist. Read also: China's commercial 'takeover' of Laos by Nikkei Asian Review.

But right now the political crisis in Thailand hinders the Thai government to move on with the project for the highspeed-rail-link between Bangkok and Vientiane. On March 12 Thailands Constitution Court ruled, that the government's legislative bill to empower the Finance Ministry to seek two trillion baht in loans for infrastructure development projects is unconstitutional, as Bangkok Post reports. This means delay for high-speed train lines to Chiang Mai, Rayong, Nong Khai (border to Vientiane in Laos) and Padang Besar, on the Malaysian border.

See a presentation of the railway project from Boten to Vientiane on youtube.com. The planned railway will have a standard-gauge track, and a maximum speed of 160km/h, less than the 200km/h initially planned, as The Nation reported. See also this video showing the planned railwa line.
The line will require 76 tunnels and 154 bridges, including two across the Mekong River, and 31 stations. These stations have been named until now: Boten, Ban Na Thong, Ban Hua Nam, Muang Xai, Ban Na Khok Tay, Huoi Phou Lai, Luang Prabang, Muong Xieng Ngeun, Ban Sen, Kasi, Ban Bua Pheouk, Ban Pha Tang, Vang Vieng, Ban Vang Mon, Ban Mang Khi, Ban Hin Heup, Phonh Hong, Ban Sakha, Ban Phonh Sung, Vientiane Neua and Vientiane Tay.
Villages will have to be relocated, if the railway is constructed, as South China Moring Post writes.

The railway project ist expected to draw an estimated 20000 Chinese construction workers into Laos. In the northern province of Oudomxay Chinese residents already make up around 15 per cent of the population of 30,000. "Chinese-owned hotels, shops and restaurants line the roads and street signs are in both Laotian and Mandarin", reports todayonline.com. Chinese companies are already investing across Laos in everything from rubber and banana plantations to construction, hydroelectric and mining projects. The railway project increases fears. "I think if the Chinese are willing to provide the money, then they're doing it for a number of reasons," says Tristan Knowles, a director at Economists at Large, a Melbourne, Australia-based think tank. "You can flood the market in Laos with Chinese goods, especially agricultural products. The meat and livestock industries in Laos may not be able to compete unless they modernise in the time it takes to build the railway." Chinese companies own an increasing number of the rubber plantations that are the mainstay of northwest Laos’ economy, reports South China Morning Post. And even in Vientiane there are more and more shops run by Chinese people. Read more in the book Vientiane: Transformations of a Lao Landscape by Marc Askew,Colin Long adn William Logan.

A Chinese-invested cement factory was inaugurated in December 2015 in Khammouane Province, expected to serve the construction of China-Laos railway project. The Jixiang cement factory, with an investment of 120 million U.S. dollars, is a BOT (Build, Operate and Transfer) project signed between China's Yunnan Provincial Energy Investment Group and Lao Ministry of Planning and Investment in March 2012. A representative of China's Yunnan Provincial Energy Investment Group told Xinhua that the designed capacity of the factory is 1 million ton a year, accounting for 20 percent of Laos' total cement production capacity.

China has announced that it will invest US$31.4 billion in the Mengla economic zone in Yunnan province, which shares a border with Luang Namtha and Phongsaly provinces in northern Laos. In September 2015 the governments of Laos and China signed a cooperation agreement to establish an economic cooperation zone in the Boten-Mohan border area, aiming to boost trade, investment and tourism in the region as inquirer.net writes. Construction started on a railway linking Yuxi to Mohan in August and preparations for Mengla airport are underway. On the Lao territory, Boten is currently designated as a specific economic zone. The zone is being developed by two Chinese companies – Yunnan Hai Cheng Industrial Group Stock Co., Ltd and Hong Kong Fuk Hing Travel Entertainment Group Ltd with a concession period of 99 years. The Chinese developers have announced that they will focus on four mega projects in the zone including a duty free center, bus station complex, warehousing and a resort that shall feature a large natural marsh, hotel, meeting hall and other relaxing places.

Chinese influence is also very apparent in Muang Xay, the capital of Oudomxay Province. Hotel Sheng Chang was established in early 2014 with a big supermarket, a casino and a restaurant. Chinese shops and advertisements fully span both sides of the road in Muang Xay. "One can find small and middle-sized Chinese auto repair shops, grocery stores, hardware stores, computer shops, guest houses, and, of course, restaurants", notes eastasiaforum.org.


Read earlier story:
Chinese money brings big change: A railway from the North of Laos to Vientiane and Thailand


This blogger thanks a lot for accurate updates, maps and great pictures to:
SkyscraperCity: Laos High Speed Train : ລົດໄຟຄວາມໄວສູງ
; Auke Koopmans and rideasia.net.


Read more:
China in Laos: Is There Cause For Worry?
Laos Railways – Information on every planned railway
Chinas Fast Track to Influence: Building a Railway in Laos

2 comments:

  1. Trade is good for everyone,the trade between laos and Thailand double each year.1 billion in 2014, 2 billion in 2015 and 4 billion in 2016. The trade between China and ASEAN was 500 billion Dollars in 2016 and one trillion dollars in a few years.ASEAN grew at an annual rate of 6%

    ReplyDelete
  2. Lao - China Railway with a price tag of 5900 Million US Dollars is almost done but the access roads between stations and existing cities have not been fully implemented yet. Therefore, it is a duty for the government to construct the new access roads to those railway stations to links with existing cities along with logistic parks and industrial estates. Furthermore, it has become necessary to perform Transport Oriented Development (TOD) around major railway stations to get more revenue to clear the loan. At least 3 stations have been targeted for TOD, started with :
    1. New City at Mohan (Chinese side) and Bo Ten (Lao Side)
    2. Luang Phrabang New City (10 km from downtown Luang Phrabang city)
    3. Oudomxay New city
    4. Vientiane New city in the Saysettha Development Zone.
    5. Na Moh New City
    More farmers in Laos have to produce agriculture products to meet Chinese standard to be eligible to export their products via those 10 railway stations that accept passengers and the other railway stations that accept cargoes.

    REF: https://vientianetimes.org.la/freeContent/FreeConten_Govt64.php

    16.9 km Luang Namtha section of Lao- China railway is 97% done. This section has Boten station (45% done) and Na Toey station (73% done) along with 7 major bridges and 3 tunnels with total distance of 10051.5 meters though with a hope to be done in October 2021. The power distribution substations for Boten and Natoey are 76% done to be finished in June 2021.

    Ref: https://laoevent.com/64950/

    Governor of Luang Phrabang has come to inspect the progress on the construction of Luang phrabang railway station at km 170+200 which is 65% done, still working up on the roof tile installation before doing the internal decoration. Furthermore, Lao - China Railway has brought Governor of Luang Phrabang to inspect the progress on the Bridge across Mekhong river at Ban Lad Han at km 143+640 with travel distance of 26.56 km
    https://luangprabangmai.blogspot.com/2021/04/blog-post_7.html

    Here is the export version of #CR200J EMUs to run Lao - China railway with max speed of 210 kph even though the existing tracks of Lao - China Railway could run at the maximum speed of 160 kph.

    There will be 2 sets of EMUs - the short one with capacity of 720 seats and the long one with capacity of 1102 seats. These sets of EMU will be delivered to Lao - China Railway in August - September 2021 for test run before opening on 2 December 2021. They have to change the color from green to the colors of Lao flag after the criticism of trash can color.

    Platelaying form Ban Xay, Mueang Xaythani of Vientiane Capital (AKA North Vientiane station) is now 80% done with a hope to finish in May 2021. Lao - China has now employed 60% of local Lao people.